The Fehmarnbelt tunnel between Denmark and Germany is being built by casting enormous concrete elements at a coastal factory, floating them out to sea by tugboat, and lowering them one by one into a prepared trench on the seafloor — a technique known as immersed tunnel construction.
What Is the Fehmarnbelt Tunnel?
The Fehmarnbelt tunnel is an 18-kilometer (11-mile) immersed road-and-rail link crossing the Fehmarn Belt strait between Rødbyhavn in Denmark and Puttgarden in Germany. When complete, it will be the longest immersed tunnel ever built — more than twice the length of the current record holder, which stretches less than four miles. Inside a single structure, the tunnel carries a four-lane motorway and two electrified rail tracks, a road-and-rail combination never before achieved at this scale in an immersed tunnel.
How Each Concrete Element Is Made and Launched
The tunnel is assembled from 89 concrete elements, each one a prefabricated section cast at a purpose-built factory on the Danish coast at Rødbyhavn. The 79 standard elements are approximately 217 meters (712 feet) long and weigh around 73,500 tonnes (roughly 81,000 US tons) apiece. Building them directly on-site eliminates the need to ship massive sections across Europe and keeps logistical complexity — and cost — tightly controlled.
Once an element is complete, it is floated out into the Fehmarn Belt on its own buoyancy, guided by tugboats. It is then positioned precisely above the trench and slowly ballasted down over the course of roughly 14 hours until it rests on the seabed. The trench reaches depths of up to 40 meters (about 130 feet) below the surface. Each element is connected to its neighbor with a rubber gasket joint and then backfilled for stability and protection.
Why a Tunnel Instead of a Bridge?
The Fehmarn Belt is one of the busiest shipping lanes in Europe. A bridge would have posed a constant navigational hazard to the large vessels that transit the strait and would have required enormous pylons that permanently disrupt both shipping traffic and the marine environment. A bridge also creates a significant barrier to bird migration across the strait.
An immersed tunnel solves all three problems at once: it sits beneath the shipping lane without interfering with surface traffic, its environmental footprint during operation is far smaller than a bridge’s, and it disappears below the seabed rather than cutting across an open-sky migration corridor. Construction costs for the tunnel were comparable to — and in detailed analysis, competitive with — the bridge alternative.
Progress: Where the Build Stands
The first element was lowered into place in May 2026, in an operation involving five tugboats and a 14-hour immersion sequence. By late September 2026, four elements were in place — roughly half a mile of completed tunnel on the seafloor, with 85 elements still to follow. At the project’s planned pace, the full sequence of immersions will continue across multiple construction seasons.
What It Means for Travel
The tunnel’s most immediate impact will be on rail travel. The train journey between Copenhagen and Hamburg currently takes around four and a half hours, routed via a ferry crossing or a long detour. Once the Fehmarnbelt tunnel opens, that journey is expected to drop to approximately two and a half hours, fundamentally reshaping rail connectivity between Scandinavia and central Europe. For road users, the fixed link will replace a ferry crossing that currently operates between the two portals.
The Bigger Engineering Picture
The Fehmarnbelt project represents the current frontier of immersed tunnel engineering — not just in total length, but in the integration of motorway and rail in a single prefabricated structure, in the scale of the on-site casting facility, and in the precision required to lower and join elements in an active, tidal marine environment. Each successful immersion brings one of Europe’s most consequential infrastructure projects one giant concrete step closer to completion.
FREQUENTLY ASKED
How long will the Fehmarnbelt tunnel be when finished? ▾
The Fehmarnbelt tunnel will be approximately 18 kilometers (11 miles) long, making it the longest immersed tunnel ever built — more than twice the length of the current record holder.
How many concrete elements does the Fehmarnbelt tunnel require? ▾
The tunnel requires 89 concrete elements in total; 79 are standard elements each around 217 meters long and weighing about 73,500 tonnes, with the remainder being special end sections.
Why was a tunnel chosen instead of a bridge across the Fehmarn Belt? ▾
A tunnel avoids disrupting one of Europe's busiest shipping lanes, reduces harm to bird migration routes, and has a smaller long-term environmental footprint than a bridge would.
How much will the Fehmarnbelt tunnel cut travel time between Copenhagen and Hamburg? ▾
The tunnel is expected to reduce the Copenhagen–Hamburg train journey from roughly four and a half hours to about two and a half hours.
What is an immersed tunnel and how does it differ from a bored tunnel? ▾
An immersed tunnel is built from prefabricated sections floated out and sunk into a seabed trench, whereas a bored tunnel is excavated through rock or soil by a tunnel-boring machine without opening the seafloor.
Where are the Fehmarnbelt tunnel elements manufactured? ▾
The concrete elements are cast at a purpose-built factory located directly on the Danish coast at Rødbyhavn, allowing finished sections to be floated straight out to their position in the strait.