Yes — in June 1969, the U.S. Army Corps of Engineers deliberately shut off the American Falls at Niagara by dumping roughly 28,000 tons of rock into the Niagara River to build a 600-foot cofferdam, leaving the falls completely dry for about five months.
Why Did Engineers Shut Off the American Falls?
The American Falls had a problem hidden in plain sight. For decades, rockfalls had been accumulating at the base of the cliff, building up a massive talus pile of broken boulders. By 1969, this debris field had quietly buried so much of the rock face that the waterfall tourists photographed was only about half the height of the bare cliff behind it. Engineers and geologists needed to study the cliff up close — something impossible to do with millions of gallons of water thundering over it every minute.
The International Joint Commission, which governs water use along the U.S.-Canada border, authorized the project. The plan was straightforward in concept, extraordinary in execution: cut off the water supply to the American Falls entirely and study the exposed rock.
How Did They Actually Do It?
In June 1969, workers dumped approximately 28,000 tons of rock and earth into the Niagara River, constructing a cofferdam stretching 600 feet from the New York shoreline to Goat Island. The cofferdam redirected all of the river’s flow toward the Canadian Horseshoe Falls, which continued roaring throughout the project.
Within days, the American Falls had run dry. What remained was a bare, ancient rock face — exposed to open air for the first time in recorded history.
What Did Engineers Find on the Bare Cliff?
Survey teams moved quickly across the exposed riverbed and cliff face. They drilled more than 40 test borings into the rock, mapped a dense network of cracks and fractures, and suspended workers in cages from crane booms to scrape loose material off the cliff face. Because the underlying shale was soft and prone to crumbling when it dried out, sprinklers were run continuously to keep the rock moist during the study.
The engineering teams got the detailed geological picture they came for — and then faced a difficult decision about the boulders.
What Happened to the Boulder Pile?
The talus pile at the base of the American Falls turned out to be more than an aesthetic nuisance. Structural analysis suggested it was likely acting as a buttress, supporting the cliff face above it. Removing the boulders could destabilize the cliff and trigger further — potentially catastrophic — rockfalls. The estimated cost to remove the debris ran as high as $10 million, with no guarantee the result would look better or be safer.
After weighing the evidence, the International Joint Commission made its call: leave the boulders exactly where they were. Let nature take its course. The talus pile that had been quietly growing for generations would stay.
When Was the American Falls Turned Back On?
In late November 1969, a dragline crane began dismantling the cofferdam, digging out the rock barrier piece by piece. Within a day, the Niagara River reclaimed its old channel. By the following afternoon, the American Falls was back at full strength — roaring, misting, and drawing tourists just as it always had.
The boulders, of course, are still there. Visitors standing at the overlook today are looking at the same debris field engineers studied in 1969, unchanged by the intervention except for the survey borings drilled into the rock. The most dramatic engineering project in Niagara’s modern history concluded with a decision to do nothing at all.
FREQUENTLY ASKED
How long was the American Falls turned off in 1969? ▾
The American Falls was dry for approximately five months, from June to late November 1969, when the cofferdam was removed and the water was restored.
How much rock was used to build the Niagara cofferdam? ▾
Workers dumped roughly 28,000 tons of rock and earth into the Niagara River to construct the 600-foot cofferdam that blocked the American Falls.
Did the Horseshoe Falls keep flowing when the American Falls was shut off? ▾
Yes — the Horseshoe Falls on the Canadian side continued flowing throughout the entire project, as the cofferdam redirected all the water to that channel.
Why did engineers decide to leave the boulders at the base of the American Falls? ▾
Analysis suggested the talus pile was likely supporting the cliff face above it, and removing it risked triggering further rockfalls, with removal costs estimated as high as $10 million.
Who authorized turning off the American Falls? ▾
The International Joint Commission, the U.S.-Canada body that governs shared waterways, authorized the project, with the U.S. Army Corps of Engineers carrying out the construction.
Can Niagara Falls be turned off again in the future? ▾
Technically yes — a cofferdam could be built again, and in fact the flow of Niagara Falls is already significantly reduced at night and in winter under a 1950 treaty that diverts water for hydroelectric power.